Actual Expenditures

 

Budgetary Financial Resources (dollars)
2014–15
Main Estimates
2014–15
Planned Spending
2014–15
Total Authorities Available for Use
2014–15
Actual Spending
(authorities used)
Difference
(actual minus planned)
158,907,952 158,907,952 165,587,501 162,002,536 3,094,584

 

Human Resources (Full-Time Equivalents[iv]—FTEs)
2014–15
Planned
2014–15
Actual
2014–15
Difference
(actual minus planned)
310 295 (15)

 

Budgetary Performance Summary for Strategic Outcome and Programs (dollars)
Strategic Outcome(s), Program(s) and Internal Services 2014-15
Main Estimates
2014-15
Planned Spending
2015-16
Planned Spending
2016-17
Planned Spending
2014-15
Total Authorities
Available for Use
2014-15
Actual Spending
(authorities used)
2013-14
Actual Spending
(authorities used)
2012-13
Actual Spending
(authorities used)
Strategic Outcome: A growing and diversified western Canadian economy
Business Development and Innovation 100,598,774 100,598,774 100,520,050 98,374,079 105,778,090 107,678,368 98,912,661 117,571,416
Community Economic Growth 34,432,043 34,432,043 34,862,792 33,393,025 34,735,060 31,958,193 62,155,737 35,377,579
Policy, Advocacy and Coordination 10,741,002 10,741,002 10,145,094 10,898,859 11,153,518 8,736,194 9,306,314 8,538,591
Strategic Outcome Subtotal 145,771,819 145,771,819 145,527,936 142,665,963 151,666,668 148,372,755 170,374,712 161,487,586
Internal Services
Subtotal
13,136,133 13,136,133 14,385,978 12,732,588 13,920,833 13,629,781 17,953,579 22,230,897
Total 158,907,952 158,907,952 159,913,914 155,398,551 165,587,501 162,002,536 188,328,291 183,718,483

Planned spending of $158.9 million for 2014–15 was increased by $6.7 million provided through new authorities and transfers, including $2.4 million from collections of repayable contributions, $2.0 million for a transfer from Agriculture and Agri-Food Canada (AAFC) related to the Canadian Beef Centre of Excellence, $2.0 million for an operating budget carry forward, and $0.3 million for various other minor adjustments.

Actual spending of $162.0 million exceeds planned spending by $3.1 million.  This variance is primarily due to frozen allotments related to personnel, other government initiatives and Federal Council.

Actual FTE utilization is lower than planned as a result of a departmental strategy to review and streamline functions to improve efficiencies for future years.  Results were achieved sooner than planned.